Project Description

Since Costa Rica is not a hydrocarbon-producing country, the supply of fuels is carried out through importation, either in the form of crude oil, intermediate products or finished products. Puerto Moín arises from the need for port infrastructure for the importation of hydrocarbons, consequently the Duques de Alba dock is built in the Caribbean Oil Terminal for the Costa Rican Petroleum Refinery (RECOPE).

Solution

The Duques de Alba pier was supported on deep driven metal pile foundations up to 45m in length. The bathymetry of the site presented depths of up to 17m, for this reason it was necessary to implement the use of a main barge (36mx14m) for the crane and driving equipment and, in addition, an auxiliary barge (36mx14m) to transport the metal piles.

 

Client:
Refinadora Costarricense de Petróleo (RECOPE).

Country:
Costa Rica

Start Date:
October 2014

End Date:
December 2015

Amounts of Work:

124 Driven Piles 914mm of diameter with lenghts that were from 30m to 45m.

Related Techniques

Related Projects

Do you have a project?

We can assist you and guarantee the best result.

Rodio Swissboring - Trabaja con nosotros

Do you have a project?

We can assist you and guarantee the best result.

Rodio Swissboring - Trabaja con nosotros