Project Description

The Guardia de Honor Overpass represents a road solution to reduce traffic in zone 10 of Guatemala City.

Solution

For the construction of the road exchanger, pile walls of 500mm and 750mm were executed with a depth of up to 16.00 meters. The structure consists of three bridges made up of: head beam, cross beams and slab. At the entrance and exit of the project, it was protected by Soil Nailing and, in addition, to control the rainwater, a system of drains connected by manholes was made..

Client:
Municipalidad de Guatemala

Country:

Guatemala

Start Date:

December 2015

End Date:

May 2016

Amounts of work:
2,482 m2 of Soil Nailing and 1,024 ml of Rotary Piles.