Project Description

The Tegucigalpa Government Civic Center project is a Public Building project that will connect 40 government agencies. The building has 24 upper levels and due to the geotechnical conditions of the area; the foundation of the project was made using foundation piles.

Solution

The foundation of the project consisted of piles ranging from 700mm to 1400mm in diameter. Their maximum depth was up to 20 meters. The drilling system used was “Rotary” type; due to the geotechnical conditions of the project and the presence of a water table, it was necessary to use a recoverable temporary casing in the first meters of the drilling..

Client:
GIA

Country:
Honduras

Start Date:
January 2017

End Date:
June 2017

Amounts of Work:

  • 1,095ml with 700mm of diameter.
  • 1,070ml with 900mm of diameter.
  • 320ml with 1,100mm of diameter.
  • 580ml with 1,400mm of diameter.

 

Related Projects

Do you have a project?

We can assist you and guarantee the best result.

Rodio Swissboring - Trabaja con nosotros

Do you have a project?

We can assist you and guarantee the best result.

Rodio Swissboring - Trabaja con nosotros