Project Description

The work consisted of the construction of piles to cement eleven buildings and / or platforms of the new Cementos Progreso plant.

Solution

The deep foundation of the new plant consisted of 552 1,000mm diameter piles with different drilling lengths, the deepest pile being 38.50m, for a total of 15,560.00 ml of drilling.

Client:
Polysius Progrefa – ThyssenKrupp

Country:

Guatemala

Start Date:

November 2013

End Date:

April 2014

Amounts of work:
15,560 ml of 1,000 mm Rotary Piles.